12/30/2020
Project Update
On December 30, 2020, the energization of newly constructed Station 255 in the Town of Henrietta was completed and the new Circuit 940 115-kV transmission line was placed in service.
12/28/2020
Construction Update
Due to the holidays, construction work is very limited and there are minimal crews on site. Work will be limited to the substation properties at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates, and at Station 23 on State Street in the City of Rochester.
Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm.
12/21/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnection work at Station 23 on State Street in the City of Rochester;
- Work associated with the overhead portion of the new 115-kV Circuits 940 and 941 transmission lines will include overhead wire work in the vicinity of Mile Wood Road in the Town of Chili;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the removal of timber mats and restoration in the vicinity of Market Street, Jetview Drive and Beahan Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm. Work may take place after hours and on Sundays at and in the vicinity of the Station 255 site off East River Road in the Town of Henrietta, and in the the vicinity of Station 418 at the Rochester Technology Park in the Town of Gates through the end of December.
12/14/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnection work at Station 23 on State Street in the City of Rochester;
- Work associated with the overhead portion of the new 115-kV Circuits 940 and 941 transmission lines will include overhead wire work in the vicinity of Mile Wood Road in the Town of Chili;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the removal of timber mats and restoration in the vicinity of Market Street, Jetview Drive and Beahan Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
12/7/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnection work at Station 23 on State Street in the City of Rochester;
- Work associated with the overhead portion of the new 115-kV Circuit 941 transmission line will include the setting of steel structures and overhead wire work in the vicinity of Ames Street, Chester Street and Colvin Street in the City of Rochester;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the removal of timber mats and restoration in the vicinity of Westside Drive, Fisher Road and Jetview Drive; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
11/30/2019
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnection work at Station 23 on State Street in the City of Rochester;
- Work associated with the overhead portion of the new 115-kV Circuit 941 transmission line will include foundation work and the setting of steel structures in the vicinity of Ames Street, Chester Street and Colvin Street in the City of Rochester;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include removal of timber mats and installation of workpads in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the removal of mats and restoration in the vicinity of Westside Drive, Pixley Road and Route 204;
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
11/23/2020
Construction Update
Due to the Thanksgiving holiday there will be limited work crews on site this week. Construction activities which may take place this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the removal of mats and restoration in the vicinity of Westside Drive, Pixley Road, Route 204, and Trabold Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
11/16/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnection work at Station 23 on State Street in the City of Rochester, and interconnection work between overhead and underground portions of the line in the vicinity of Beahan Road, the Rochester and Southern Railroad and Brooks Road in the Towns of Chili and Gates;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the removal of mats and restoration in the vicinity of Westside Drive, Pixley Road and Route 204;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
11/9/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnection work at Station 23 on State Street in the City of Rochester, pulling fiber optic cable in the vicinity of Frontier Field, and interconnection work between overhead and underground portions of the line in the vicinity of Beahan Road, the Rochester and Southern Railroad and Brooks Road in the Towns of Chili and Gates;
- Work associated with the overhead portion of the new 115-kV Circuit 941 transmission line will include overhead wire work in the vicinity of West Broad Street, Industrial Street, Allen Street and I-490;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the removal of mats and restoration in the vicinity of Coldwater Road and Trabold Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
11/2/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnect preparation work at Station 23 on State Street in the City of Rochester, and interconnect between overhead and underground portions of the line in the vicinity of Beahan Road, the Rochester and Southern Railroad and Brooks Road in the Towns of Chili and Gates;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the pulling of fiber optic cable, and the removal of mats and restoration in the vicinity of Coldwater Road and Trabold Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
10/26/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include interconnect preparation work at Station 23 on State Street in the City of Rochester, and interconnect between overhead and underground portions of the line in the vicinity of Beahan Road, the Rochester and Southern Railroad and Brooks Road in the Towns of Chili and Gates;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates will include the pulling of fiber optic cable, and the removal of mats and restoration in the vicinity of Coldwater Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
10/19/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include preparation of conduit for wire installation in the vicinity of Frontier Field in the City of Rochester , and restoration activities in the vicinity of Beahan Road and Little Black Creek in the Towns of Chili and Gates;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
10/12/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include wire installation and related activity in the vicinity of Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include wire installation and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include assembling and setting steel structures in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm. Work may take place after hours and on Sundays at the Station 255 site off East River Road in the Town of Henrietta through the end of October.
10/5/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include wire installation and related activity in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the installation of conduit, placement of timber mats and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the overhead portions of the new 115-kV Circuit 940 and 941 transmission lines and 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
9/28/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation and timber mat removals in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the installation of conduit and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the overhead portions of the new 115-kV Circuit 940 and 941 transmission lines and 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
9/21/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation and timber mat removals in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the installation of conduit and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the overhead portions of the new 115-kV Circuit 940 and 941 transmission lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
9/14/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation and timber mat removals in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the installation of conduit and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the overhead portions of the new 115-kV Circuit 940 and 941 transmission lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
9/8/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation and timber mat removals in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the preparation of conduit for conductor installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
8/31/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation and timber mat removals in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the preparation of conduit for conductor installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
8/24/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the preparation of conduit for conductor installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include the assembling and erection of steel structures, and overhead wire work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area, including the removal of timber mats in the vicinity of Krenzer Road and Ballantyne Road in the Town of Chili; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
8/17/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation in the vicinity of Pixley Road, Coldwater Road, Route 204 and Trabold Road, and the placement of timber matting in advance of conductor installation in the vicinity of Fisher Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include the preparation of conduit for conductor installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include the assembling and erection of steel structures in the vicinity of Mile Wood road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
8/10/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation in the vicinity of Pixley Road, Buffalo Road and Station 418 at the Rochester Technology Park, and the placement of timber matting in advance of conductor installation in the vicinity of Fisher Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include conduit preparation and installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include the assembling and erection of steel structures in the vicinity of Mile Wood road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
8/3/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Gates and Chili will include conductor installation in the vicinity of Pixley Road, Buffalo Road and Station 418 at the Rochester Technology Park, and the placement of timber matting in advance of conductor installation in the vicinity of Wegmans Market Street;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include conduit preparation and installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include the assembling and erection of steel structures in the vicinity of Mile Wood road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
7/27/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town Gates will include conductor installation in the vicinity of Pixley Road, Buffalo Road and Station 418 at the Rochester Technology Park;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include conduit preparation and installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include the erection of steel structures in the vicinity of Mile Wood road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
7/20/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include preparation of conduit for conductor installation in the vicinity of Pixley Road and Trabold Road, and conductor installation in the vicinity of Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include conduit preparation and installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include overhead wire work in the vicinity of Buffalo Road, West Avenue and Ames Street;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
7/13/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include preparation of conduit and vaults for conductor installation in the vicinity of Trabold Road, and preparation for the installation of underground conductor in the vicinity of Pixley Road, West Side Drive and RG&E's Station 67 off of Fisher Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include conduit preparation and installation in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include overhead wire work in the vicinity of Buffalo Road, West Avenue and Ames Street;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
7/6/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work and preparation of conduit and vaults for conductor installation in the vicinity of Trabold Road, and preparation for the installation of underground conductor in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and related activity in the vicinity of Beahan Road and Little Black Creek;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
6/29/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work and preparation of conduit and vaults for conductor installation in the vicinity of Trabold Road, and preparation for the installation of underground conductor in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and paving of the parking lot at Frontier Field, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
6/22/2019
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work and preparation of conduit and vaults for conductor installation in the vicinity of Trabold Road, preparation for the installation of underground conductor, restoration and related activity in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and the preparation of conduit for tie-ins in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
6/15/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work and preparation of conduit and vaults for conductor installation in the vicinity of Trabold Road, preparation for the installation of underground conductor, restoration and related activity in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and the preparation of conduit for tie-ins in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
6/8/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work and preparation of conduit and vaults for conductor installation in the vicinity of Trabold Road, preparation for the installation of underground conductor, restoration and related activity in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and the preparation of conduit for tie-ins in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
6/1/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work, preparation of conduit and vaults for conductor installation in the vicinity of Trabold Road, preparation for the installation of underground conductor, restoration and related activity in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and the preparation of conduit for tie-ins in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include overhead wire work in the vicinity of Chili Avenue, Cairn Street, Copley Street, Wilbur Street, Buffalo Road, West Avenue and Ames Street;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
5/25/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work, preparation of conduit and vaults for conductor installation, mobilization for the installation of underground conductor, restoration and related activity in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and the preparation of conduit for tie-ins in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include the removal of timber mats and restoration in the vicinity of Scottsville Road and Mile Wood Road;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include overhead wire work in the vicinity of Chili Avenue, Cairn Street, Copley Street, Wilbur Street, Buffalo Road, West Avenue and Ames Street;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
5/18/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work, preparation of conduit and vaults for conductor installation, mobilization for the installation of underground conductor, restoration and related activity in the vicinity of Trabold Road, Coldwater Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include restoration and the preparation of conduit for tie-ins in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include the removal of timber mats and restoration in the vicinity of Scottsville Road and Mile Wood Road;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include overhead wire work in the vicinity of Chili Avenue, Cairn Street, Copley Street, Wilbur Street, Buffalo Road, West Avenue and Ames Street;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
5/11/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include the removal of timber mats and restoration in the vicinity of Scottsville Road and Mile Wood Road;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include overhead wire work in the vicinity of Chili Avenue, Cairn Street, Copley Street, Wilbur Street, Buffalo Road, West Avenue and Ames Street;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
5/4/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include the removal of timber mats and restoration in the vicinity of Scottsville Road and Mile Wood Road;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include the running of ropes in preparation for wire work in the vicinity of Chili Avenue, Cairn Street, Copley Street, Wilbur Street, Buffalo Road, West Avenue and Ames Street;
- Work associated with 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include foundation work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
4/27/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling and related activity, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Pixley Road, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include overhead wire work in the vicinity of Scottsville Road and Mile Wood Road;
- Work associated with 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include foundation work in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Restoration work and maintenance of environmental controls will continue throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
4/20/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling and related activity, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Pixley Road, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include overhead wire work in the vicinity of Scottsville Road and Mile Wood Road;
- Restoration work and maintenance of environmental controls throughout the project area; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
4/13/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling and related activity, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include overhead wire work in the vicinity of Scottsville Road and Mile Wood Road;
- Restoration work throughout the project area, including the planting of landscape vegetation in the City of Rochester in the vicinity of Brown Street, Silver Street, Madison Street and King Street; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
4/6/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling and related activity, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include the setting of structures, and overhead wire work in the vicinity of Scottsville Road and Mile Wood Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
3/30/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling and related activity, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include the removal of timber mats and other restoration activities in the vicinity of Paul Road, Fisher Road and the Rochester and Southern Railroad, and overhead wire work in the vicinity of Scottsville Road and Mile Wood Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
3/23/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling and related activity, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include the removal of timber mats and other restoration activities in the vicinity of Paul Road, Fisher Road and the Rochester and Southern Railroad, and overhead wire work in the vicinity of Scottsville Road and Mile Wood Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
3/16/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling and related activity, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include overhead wire work in the vicinity of Paul Road, Fisher Road and the Rochester and Southern Railroad, and the setting of structures in the vicinity of Scottsville Road and Mile Wood Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
3/9/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include overhead wire work in the vicinity of Paul Road, Fisher Road and the Rochester and Southern Railroad;
- Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta will include timber mat removals and restoration in the vicinity of East River Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
3/2/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include overhead wire work in the vicinity of Paul Road, Fisher Road and the Rochester and Southern Railroad;
- Work associated with the new overhead Circuit 940 in the Town of Gates will include timber mat removals and restoration in the vicinity of Brooks Avenue and the Rochester and Southern Railroad;
- Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta will include timber mat removals and restoration in the vicinity of East River Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
2/24/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town Chili will include overhead wire work in the vicinity of Paul Road, Fisher Road, Beahan Road and the Rochester and Southern Railroad;
- Work associated with the new overhead Circuit 940 in the Town of Gates will include timber mat removals and restoration in the vicinity of Brooks Avenue and the Rochester and Southern Railroad, and tree cutting and removal in the vicinity of Caroline Drive;
- Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta will include timber mat removals and restoration in the vicinity of East River Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
2/17/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili will include assembling and setting structures in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the new overhead 115-kV Circuit 941 in the Town of Gates will include overhead wire work in the vicinity of Paul Road, Fisher Road, Beahan Road and the Rochester and Southern Railroad;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include foundation work and structure setting in the vicinity of Love Street, Brown Street, Silver Street, Dengler Street and Saxton Street; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
2/10/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work, preparation of conduit for tie-ins and conductor installation, restoration and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal directional drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili will include assembling and setting structures in the vicinity of Mile Wood Road, the Genesee River and East River Road;
- Work associated with the new overhead 115-kV Circuit 941 in the Town of Gates will include overhead wire work in the vicinity of Brooks Avenue, Chili Avenue, I-390 and the Rochester and Southern Railroad;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include foundation work and structure setting in the vicinity of Love Street, Brown Street, Silver Street, Dengler Street and Saxton Street; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm. Work may take place after hours and on Sundays at the Station 255 site off East River Road in the Town of Henrietta through the end of April, and at the underground boring location at Frontier Field in the City of Rochester.
2/3/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include underground boring and related activity in the vicinity of Frontier Field and I-490, and horizontal direction drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili will include assembling and setting structures in the vicinity of Mile Wood Road, the Genesee River and East River Road, and gravel road work and restoration in the vicinity of Ballantyne Road, Brook Road and Krenzer Road;
- Work associated with the new overhead 115-kV Circuit 941 in the Town of Gates will include overhead wire work in the vicinity of Brooks Avenue, the Rochester & Southern Railroad and Chili Avenue;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include foundation work and structure setting in the vicinity of Love Street, Silver Street, Brown Street, Canal Street and Industrial Street; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm.
1/27/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include excavation and related activity in the vicinity of Frontier Field and I-490, and horizontal direction drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili will include assembling and setting structures in the vicinity of Mile Wood Road, the Genesee River and East River Road, and gravel road work and restoration in the vicinity of Ballantyne Road, Brook Road and Krenzer Road;
- Work associated with the new overhead 115-kV Circuit 941 in the Town of Gates will include the running of ropes in preparation for wire work in the vicinity of Brooks Avenue, I-390 and the Rochester and Southern Railroad;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include foundation work and structure setting in the vicinity of Child Street, Wright Street, York Street, Brown Street, Silver Street, King Street, Canal Street and Industrial Street; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm. Work will take place on Sundays at the Station 255 site off East River Road in the Town of Henrietta through the end of January, excluding the holiday time periods.
1/20/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road, and timber mat removals in the vicinity of Trabold Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include excavation and related activity in the vicinity of Frontier Field and I-490, and horizontal direction drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili will include assembling and setting structures in the vicinity of Mile Wood Road, the Genesee River and East River Road, and gravel road work and restoration in the vicinity of Ballantyne Road, Brook Road and Krenzer Road;
- Work associated with the new overhead 115-kV Circuit 941 in the Town of Gates will include the running of ropes in preparation for wire work in the vicinity of Brooks Avenue, I-390 and the Rochester and Southern Railroad;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include foundation work in the vicinity of Colvin Street, Brown Street and Silver Street; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, at Station 80 off Lehigh Station Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
1/13/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include excavation and related activity in the vicinity of Frontier Field and I-490, and horizontal direction drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili will include assembling and setting structures in the vicinity of Mile Wood Road, the Genesee River and East River Road, and timber mat removals, gravel road work and restoration in the vicinity of Ballantyne Road, Brook Road and Krenzer Road;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include foundation work in the vicinity of West Avenue;
- Work associated with 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include foundation work in the vicinity of Mile Wood Road, the Genesee River and East River Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.
1/6/2020
Construction Update
Construction activities planned for this week include:
- Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include horizontal directional drilling, duct bank work and related activity in the vicinity of Jetview Drive, Pixley Road, Route 204, Trabold Road and Buffalo Road;
- Work associated with the underground portion of the new 115-kV Circuit 941 transmission line will include excavation and related activity in the vicinity of Frontier Field and I-490, and horizontal direction drilling and related activity in the vicinity of Beahan Road and Little Black Creek;
- Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili will include assembling and setting structures in the vicinity of Mile Wood Road, the Genesee River and East River Road, and timber mat removals and restoration in the vicinity of Brook Road;
- Work associated with the new overhead 115-kV Circuit 941 in the City of Rochester will include foundation work in the vicinity of West Avenue;
- Work associated with 345-kV NYPA tap lines in the Towns of Chili and Henrietta will include foundation work in the vicinity of Mile Wood Road, the Genesee River and East River Road; and
- Work within the substation properties will continue at the Station 255 site off East River Road in the Town of Henrietta, and at Station 418 in the vicinity of the Rochester Technology Park in the Town of Gates.