A large transmission project, such as the Rochester Area Reliability Project, can take several years to build from its initial planning stage to energization. RG&E commenced construction at Station 80 (located in the Town of Henrietta off of Lehigh Station Road) in October 2014 working on bay 4, completing this portion of RARP in April 2017. RG&E recommenced construction in early 2018, with the initial work focused on the underground portion of Circuit 940 in the Town of Gates and the wetland mitigation project off Ballantyne Road in the Town of Chili. Work at Station 255 (located in the Town of Henrietta off of East River Road) and the overhead Circuit 40 (in the Town of Henrietta) began in the fall of 2018. Site preparation related to construction of the overhead transmission lines in the Town of Chili began in February 2019. Transmission line work in the City of Rochester will commence late 2019, and the RARP will be placed into service by late 2020/early 2021.

Keep up to date on the status of the RARP by reviewing the below weekly construction schedule updates, including current locations with associated scopes of work:

 

7/8/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, will include horizontal directional drilling and related activity in the vicinity of Chili Avenue, Trabold Road and Pixley Road, and general site clean up and restoration;
  • Work associated with the overhead I-490 portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, will include the installation of steel structures in the vicinity of Trabold Road and I-490;
  • Work associated with the underground portion of the new 115-kV Circuit 941 transmission line in the City of Rochester will include duct bank trench excavation in the vicinity of Plymouth Avenue and State Street;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include restoration and the removal of timber mats; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad will included foundation drilling in the vicinity of Paul Road ad Ballantyne Road, and installation of timber mats, tree and brush clearing and vegetation and debris removal in the vicinity of Brook Road and Coates Road;
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta in the vicinity of East River Road, will include restoration and the removal of timber mats; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, construction of the control building, movement of soils, maintenance of environmental controls, and material delivery.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm. Through the spring and summer, work at Station 255 may extend past 6:00 pm, but not later than sundown.

7/1/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, will include horizontal directional drilling and related activity in the vicinity of Chili Avenue, Trabold Road and Pixley Road, and general site clean up and restoration;
  • Work associated with the underground portion of the new 115-kV Circuit 941 transmission line in the City of Rochester will include duct bank trench excavation in the vicinity of Plymouth Avenue and State Street, and Beahan Road;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include restoration and the removal of timber mats; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad will included foundation drilling and structure installation in the vicinity of Ballantyne Road, and installation of timber mats, tree and brush clearing and vegetation and debris removal in the vicinity of Brook Road and Coates Road;
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta in the vicinity of East River Road, will include overhead wire work; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, construction of the control building, movement of soils, maintenance of environmental controls, and material delivery.

6/24/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, will include horizontal directional drilling and related activity in the vicinity of Chili Avenue, Trabold Road and Pixley Road, and general site clean up and restoration;
  • Work associated with the underground portion of the new 115-kV Circuit 941 transmission line in the City of Rochester will include duct bank trench excavation in the vicinity of Plymouth Avenue and State Street;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include restoration and the removal of timber mats; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad will included foundation drilling and structure installation in the vicinity of Paul Road, Fisher Road and Beahan Road, and installation of timber mats, tree and brush clearing and vegetation and debris removal south of Ballantyne Road;
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta in the vicinity of East River Road, will include overhead wire work; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, construction of the control building, movement of soils, maintenance of environmental controls, and material delivery.

6/17/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with trenching on the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include proofing and mandrelling (cleaning) conduit, general site clean up, and restoration; 
  • Work associated with drilling on the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, will include horizontal directional drilling and related activity in the vicinity of Chili Avenue, Trabold Road, and Pixley Road;
  • Work associated with the underground portion of the new 115-kV Circuit 941 transmission line in the City of Rochester will include duct bank trench excavation in the vicinity of Plymouth Avenue and State Street;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include restoration and the removal of timber mats; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad will included foundation drilling and structure installation in the vicinity of Paul Road, Fisher Road and Beahan Road, and installation of timber mats, tree and brush clearing and vegetation and debris removal south of Ballantyne Road;
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta in the vicinity of East River Road, will include the preparation for and stringing of conductor; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, framing of the control building, movement of soils, maintenance of environmental controls, and material delivery.

6/10/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with trenching on underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, manhole installation, restoration and maintenance of environmental controls; 
  • Work associated with drilling on the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, will include horizontal directional drilling and related activity in the vicinity of Chili Avenue, Trabold Road, and Pixley Road;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include restoration and the removal of timber mats; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad will included foundation drilling and structure installation in the vicinity of Paul Road, Fisher Road and Beahan Road, and installation of timber mats, tree and brush clearing and vegetation and debris removal south of Ballantyne Road;
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta in the vicinity of East River Road, will include the setting of transmission structures and installation of timber mats; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

6/3/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with trenching on underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, manhole installation, restoration and maintenance of environmental controls; 
  • Work associated with drilling on the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, includes horizontal directional drilling under Chili Avenue, mobilization of a drill rig and the preparation for drilling in the vicinity of Trabold Road, and installation of timber mats and work pads in the vicinity of Pixley Road;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include completion, energization and inspection of the newly installed circuit; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Paul Road, Fisher Road and Beahan Road, will include foundation drilling, structure installation, installation of timber mats, tree and brush clearing, and vegetation and debris removal;
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta in the vicinity of East River Road, will include the mobilization of work crews and delivery of material; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

5/27/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, manhole installation, restoration and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, in the vicinity of Chili Avenue, Westside Drive and Red Coat Circle, will include installation of matting, and horizontal directional drilling under Chili Avenue;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include pulling in and attaching conductor and fiber optic cable. From June 1 through June 3, crews may be working from sunrise until sundown with activities to include wrecking out old structures, installation of new structures, and wire work to transition conductor from the existing Circuit 906 to the newly relocated structures; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Paul Road, Fisher Road and Beahan Road, will include foundation drilling, structure installation, installation of timber mats, tree and brush clearing, and vegetation and debris removal; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm. Through the spring and summer, work at Station 255 may extend past 6:00 pm, but not later than sundown. In addition, crews will be working through the weekend, June 1-3, in the vicinity of Ballantyne Road and Krenzer Road, as noted above, with work starting as early as sunrise and continuing up until sundown.

5/20/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, manhole installation, restoration and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates, in the vicinity of Chili Avenue, Westside Drive and Red Coat Circle, will include installation of matting, and mobilization and commencement of horizontal directional drilling under Chili Avenue;
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include ongoing structure work and the preparation for wire work; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Paul Road, Fisher Road and Beahan Road, will include foundation drilling, structure installation, installation of timber mats, tree and brush clearing, and vegetation and debris removal; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

5/13/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, manhole installation, restoration and maintenance of environmental controls; 
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include ongoing structure work and the preparation for wire work; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Paul Road, Fisher Road and Beahan Road, will include installation of timber mats, tree and brush clearing, and vegetation and debris removal; 
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery; and
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta, in the vicinity of East River Road, will include the spotting of steel structure arms.

5/6/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, manhole installation, restoration and maintenance of environmental controls; 
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include foundation work, and the spotting, assembling and installation of steel structures; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad, will include mowing and tree and brush clearing in the vicinity of Paul Road, Fisher Road and Beahan Road, and vegetation and debris removal; 
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery; and
  • Work associated with the new overhead 345-kV Circuit 40 in the Town of Henrietta, in the vicinity of East River Road, will include the spotting of steel structures.

4/29/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, manhole installation, mowing and maintenance of environmental controls; 
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road, Brook Road and Krenzer Road, will include foundation work, and the spotting, assembling and installation of steel structures; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad, will include mowing and brush clearing in the vicinity of Paul Road and Fisher Road, and vegetation and debris removal; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

4/22/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Fisher Road and Jetview Drive, will include the removal of matting, clean up and restoration; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, mowing and maintenance of environmental controls; 
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road and Brook Road, will include foundation work and pouring cement, and the spotting, assembling and installation of steel structures; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad, will include mowing and brush clearing in the vicinity of Paul Road and Fisher Road, and vegetation and debris removal; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

4/15/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Fisher Road and Jetview Drive, will include the removal of matting, clean up and restoration; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include duct bank trench excavation, mowing and maintenance of environmental controls; 
  • Work associated with the relocated 115-kV Circuit 906 in the Town of Chili, along the Rochester and Southern Railroad in the vicinity of Ballantyne Road and Brook Road, will include foundation work and pouring cement, and the spotting and assembling of steel structures; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941 in the Town of Chili, along the Rochester and Southern Railroad, will include tree and brush clearing in the vicinity of Paul Road and Fisher Road, and vegetation and debris removal in the vicinity of Ballantyne Road, Paul Road and Fisher Road; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

4/8/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Fisher Road and Jetview Drive, will include the removal of matting, clean up and restoration; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Buffalo Road, Coldwater Road and Trabold Road, will include surveying the transmission line center line, equipment mobilization and mowing; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941, and relocated 115-kV Circuit 906, in the Town of Chili, along the Rochester and Southern Railroad, will include tree and brush clearing in the vicinity of Ballantyne Road heading north toward Paul Road, and the spotting and assembling of steel structures, and vegetation removal in the vicinity of Brook Road and Krenzer Road; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm. Through the spring and summer, work at Station 255 may extend past 6:00 pm, but not later than sundown.

4/1/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Towns of Chili and Gates will include general site clean up, restoration, maintenance of environmental controls and site inspections; 
  • Work associated with the new overhead 115-kV Circuits 940 and 941, and relocated 115-kV Circuit 906, in the Town of Chili, along the Rochester and Southern Railroad, will include installation of matting for access and work pads, tree and brush clearing, installation of gravel access roads, and spotting of steel structures in the vicinity of Brook Road and Krenzer Road; 
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road related to the overhead I-490 crossing, will include the installation of matting for access and work pads, tree and brush clearing, foundation drilling, and concrete pouring; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

3/25/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include proofing and mandrelling (cleaning) conduit, general site clean up, and restoration; 
  • Work associated with the relocation of the 115-kV Circuit 906 in the Town of Chili along the Rochester and Southern Railroad will include installation of matting for access and work pads, tree and brush clearing, the installation of gravel access off of Krenzer Road, and the spotting of steel structures in the vicinity of Ballantyne Road, Brook Road and Krenzer Road; 
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road related to the overhead I-490 crossing, will include the installation of matting for access and work pads, tree and brush clearing, foundation drilling, and concrete pouring; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

3/18/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include proofing and mandrelling (cleaning) conduit, general site clean up, and restoration; 
  • Work associated with site preparation for Circuit 906 in the Town of Chili along the Rochester and Southern Railroad will include installation of matting for access and work pads, tree and brush clearing, and the installation of gravel access along Coates Road and off of Krenzer Road; 
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road related to the overhead I-490 crossing, will include the installation of matting for access and work pads, tree and brush clearing, foundation drilling and concrete pouring; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, movement of soils, maintenance of environmental controls, and material delivery.

3/11/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; 
  • Work associated with site preparation for Circuit 906 in the Town of Chili along the Rochester and Southern Railroad will include installation of matting for access, tree and brush clearing, and the installation of gravel access along Coates Road and off of Krenzer Road; 
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road related to the overhead I-490 crossing, will include the installation of matting for access and work pads, tree and brush clearing, and the commencement of foundation drilling; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, tree and brush clearing at the Genesee River, maintenance of environmental controls, and material delivery.

3/4/2019

Construction Update

Construction activities planned for this week include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; 
  • Work associated with site preparation for Circuit 906 in the Town of Chili along the Rochester and Southern Railroad will include installation of matting for access, tree and brush clearing, and the installation of gravel access along Coates Road; 
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road related to the overhead I-490 crossing, will include the installation of matting for access and work pads, tree and brush clearing, and mobilization of drilling crews; and
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include foundation installation and other subgrade work, maintenance of environmental controls, and material delivery.

2/25/2019

Construction Update

Construction activities planned for this week, weather conditions permitting, include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; 
  • Work associated with site preparation for Circuit 906 in the Town of Chili along the Rochester and Southern Railroad will include installation of matting for access, tree and brush clearing, and the installation of gravel access along Coates Road; 
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road related to the overhead I-490 crossing, will include the installation of matting for access and work pads, and tree and brush clearing; and
  • Limited work at the Station 255 site, off East River Road in the Town of Henrietta, will include maintenance of environmental controls, mobilization of crews for in-ground works, and material delivery.

2/18/2019

Construction Update

Construction activities planned for this week, weather conditions permitting, include:

  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; 
  • Work associated with site preparation for Circuit 906 in the Town of Chili, in the vicinity of Brook Road, will include installation of matting for access, and tree and brush clearing; and
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road, will include removal, relocation and installation of matting for access to the overhead I-490 crossing.

2/11/2019

Construction Update

Construction activities planned for this week, weather conditions permitting, include:

  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, grading and topsoil removal, and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; 
  • Work associated with site preparation for Circuit 906 in the Town of Chili, in the vicinity of Brook Road, will include installation of matting for access, and tree and brush clearing; and
  • Work associated with the new 115-kV Circuit 940 transmission line in the Town of Gates, in the vicinity of Trabold Road, will include removal, relocation and installation of matting for access to the overhead I-490 crossing.

2/4/2019

Construction Update

Construction activities planned for this week include:

  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, grading and topsoil removal, and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; and
  • Work associated with site preparation for Circuit 906 in the Town of Chili, in the vicinity of Brook Road, will include installation of matting for access, and tree and brush clearing.

1/28/2019

Construction Update

Construction activities planned for this week include:

  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, grading and topsoil removal, snow removal and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; and
  • Work associated with site preparation for Circuit 906 in the Town of Chili, in the vicinity of Brook Road and Ballantyne Road, will include installation of matting for access, and tree and brush clearing.

1/21/2019

Construction Update

Construction activities planned for this week, all weather depending, include:

  • Snow removal at all active project locations, including Station 255 off East River Road in the Town of Henrietta, along the Rochester and Southern Railroad between Brook Road and Ballantyne Road in the Town of Chili, and between Jetview Drive and Fisher Road in the Town of Chili;
  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, grading and topsoil removal, and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; and
  • Work associated with site preparation for Circuit 906 in the Town of Chili between Brook Road and Ballantyne Road will include installation of matting for access, and tree and brush clearing.

1/14/2019

Construction Update

Construction activities planned for this week include:

  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, grading and topsoil removal, and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive and Fisher Road, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; and
  • Work associated with site preparation for Circuit 906 in the Town of Chili between Brook Road and Ballantyne Road will include installation of matting and gravel for access, and tree and brush clearing.

1/7/2019

Construction Update

Construction activities planned for this week include:

  • Work at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, grading and topsoil removal, building demolition, access road development, and maintenance of environmental controls; 
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive, will include excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; and
  • Work associated with Circuit 40 in the Town of Henrietta east of East River Road will include maintenance of environmental controls as necessary.

1/2/2019

Construction Update

Construction activities planned for this week include:

  • Work (weather and site conditions permitting) at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, access road development, and maintenance of environmental controls;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, in the vicinity of Jetview Drive, includes excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; and
  • Civil work associated with Circuit 40 in the Town of Henrietta will take place in the vicinity of East River Road and Lehigh Station Road, and will include the installation/maintenance of environmental controls, and clearing/removal of trees and brush.

12/26/2018

Construction Update

Construction activities planned for this week include:

  • Work (weather and site conditions permitting) at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, access road development, and maintenance of environmental controls; and
  • Civil and work associated with Circuit 40 in the Town of Henrietta will take place in the vicinity of East River Road and Lehigh Station Road, and will include the installation/maintenance of environmental controls, and clearing/removal of trees and brush.

12/17/2018

Construction Update

Construction activities planned for this week include:

  • Work (weather and site conditions permitting) at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, access road development, demolition of old structures on site, and maintenance of environmental controls;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, west of Fisher Road, includes excavation of the duct bank trench, installation of conduit, manhole installation, and restoration; 
  • Civil work associated with Circuit 40 in the Town of Henrietta will take place in the vicinity of East River Road and will include the installation of timber mats, access road development, installation of environmental controls, and clearing/removal of trees and brush; and
  • Foundation installation activities, including drilling and pouring of concrete, associated with Circuit 40 will take place east of East River Road in the Town of Henrietta.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm, with nighttime work depending on weather conditions. Work may also take place on Sundays between the hours of 7:00 am and 5:00 pm at the Station 255 site.

12/10/2018

Construction Update

Construction activities planned for this week include:

  • Work (weather and site conditions permitting) at the Station 255 site, off East River Road in the Town of Henrietta, will include the installation/compaction of the station platform, access road development, demolition of old structures on site, and maintenance of environmental controls;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili, west of Fisher Road, includes excavation of the duct bank trench, installation of conduit, and trench restoration; 
  • Work associated with Circuit 40 in the Town of Henrietta will take place in the vicinity of East River Road and will include the installation of timber mats at lay down areas and work pads, access road development, installation of environmental controls, and clearing/removal of trees and brush; and
  • The commencement of foundation drilling activities related to Circuit 40 will take place west of East River Road in the Town of Henrietta.


12/3/2018

Construction Update

Construction activities planned for this week include:

  • Work, weather and site conditions permitting, at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes stripping and stockpiling topsoil, processing and removal of vegetative debris, access road development, and maintenance of environmental controls;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili west of Fisher Road. Work to be performed includes excavation of the duct bank trench, installation of conduit, and trench restoration; and
  • Work associated with Circuit 40 in the Town of Henrietta. Work will take place in the vicinity of East River Road and will include the installation of timber mats, access road development, installation of environmental controls, and clearing/removal of trees and brush.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 6:00 pm, with nighttime work depending on weather conditions. Work may also take place on Sundays between the hours of 7:00 am and 5:00 pm at the Station 255 site.

11/26/2018

Construction Update

Construction activities planned for this week include:

  • Continued work, weather permitting, at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes stripping and stockpiling topsoil, processing and removal of vegetative debris, and maintenance of environmental controls;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili west of Fisher Road. Work to be performed includes excavation of the duct bank trench, installation of conduit, and trench restoration; and
  • Work associated with Circuit 40 in the Town of Henrietta. Work will take place in the vicinity of East River Road and will include the installation of timber mats, and clearing of trees and brush.

11/19/2018

Construction Update

Construction activities planned for this week include:

  • Continued work, weather permitting, at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes stripping and stockpiling topsoil, and processing and removal of vegetative debris;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili in the vicinity of Fisher Road. Work to be performed includes excavation of the duct bank trench, installation of conduit, and trench restoration; and
  • Work associated with Circuit 40 in the Town of Henrietta. Work will take place in the vicinity of East River Road and will include the installation of timber mats and clearing of trees and brush.

Please note that crews will not be working during the Thanksgiving holiday. Crews will return to work on Monday, November 26, 2018.

11/12/2018

Construction Update

Construction activities planned for this week include:

  • Continued work at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes stripping and stockpiling topsoil, and processing and removal of vegetative debris;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili in the vicinity of Fisher Road. Work to be performed includes excavation of the duct bank trench across Fisher Road, installation of conduit, and road restoration; and
  • Continued work associated with the installation of railway crossings within the Rochester & Southern Railroad property in the Town of Chili.

11/5/2018

Construction Update

Construction activities planned for this week include:

  • Continued work at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes tree and brushing clearing, grading, access road development, and installation of environmental controls;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili in the vicinity of Fisher Road. Work to be performed includes excavation of the duct bank trench, installation of conduit, and installation of environmental controls; and
  • Continued work associated with the installation of railway crossings within the Rochester & Southern Railroad property in the Town of Chili.

10/29/2018

Construction Update

Construction activities planned for this week include:

  • Continued work at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes tree and brushing clearing, grading, access road development, and installation of environmental controls;
  • Work associated with the underground portion of the new 115-kV Circuit 940 transmission line in the Town of Chili in the vicinity of Fisher Road. Work to be performed includes excavation of the duct bank trench, installation of conduit, and installation of environmental controls; and
  • Continued work associated with the installation of railway crossings within the Rochester & Southern Railroad property in the Town of Chili

10/22/2018

Construction Update

Construction activities planned for this week include:

  • Site preparation activities at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes installation of timber mats and environmental controls, mobilization of work equipment and trailers, and tree and brush clearing;
  • Limited tree/brush cutting associated with the location of underground facilities within the Rochester & Southern Railroad property in the Town of Chili; and
  • Continued work associated with the installation of railway crossings continues within the Rochester & Southern Railroad property in the Town of Chili in the vicinity of Brook Road and Krenzer Road.

10/15/2018

Construction Update

Construction activities planned for this week include:

  • The commencement of site preparation activities at the Station 255 site off East River Road in the Town of Henrietta. Work to be performed includes installation of timber mats and environmental controls, mobilization of work equipment and trailers, and tree and brush clearing; and
  • Continued work associated with the installation of railway crossings continues within the Rochester & Southern Railroad property in the Town of Chili in the vicinity of Ballantyne Road, Brook Road and Krenzer Road.

10/8/2018

Construction Update

Work associated with the installation of railway crossings continues within the Rochester & Southern Railroad property in the Town of Chili in the vicinity of Fisher Road, Paul Road, Brook Road and Krenzer Road.

It is expected that work crews will be mobilized and site preparation activities will commence next week at the Station 255 site off East River Road in the Town of Henrietta.

Weeks of 9/24/2018 & 10/1/2018

Construction Update

Work associated with the installation of railway crossings continues within the Rochester & Southern Railroad property in the Town of Chili in the vicinity of Ballantyne Road, Brook Road and Krenzer Road.

9/17/2018

Construction Update

Work crews will be performing maintenance work associated with the installation of temporary railway crossings within the Rochester & Southern Railroad property in the Town of Chili in the vicinity of Ballantyne Road and Brook Road.

 

9/10/2018

Construction Update

Work crews will be performing maintenance work associated with the installation of temporary railway crossings within the Rochester & Southern Railroad property commencing in the vicinity of Beahan and Fisher Roads in the Town of Chili and working south.

 

9/4/2018

Construction Update

Work crews are expected to begin mobilizing this week for upcoming work within the Rochester & Southern Railroad property in the vicinity of Fisher Road in the Town of Chili.

8/27/2018

Construction Update

Work crews are expected to commence mowing activities this week along the Rochester and Southern Railroad in the Town of Chili in the vicinity of Fisher Road. They will proceed generally from the north to south.

August 2018

Project Update

With the exception of limited field studies, survey and maintenance, construction crews are currently inactive. Remobilization is expected to occur in late August to early September.

Weeks of 7/23/2018 & 7/30/2018

Construction Update

Work continues at the Ballantyne Road wetland mitigation site in the Town of Chili. Activities include seed planting, watering newly planted trees and equipment demobilization.

Weeks of 7/9/2018 & 7/16/2018

Construction Update

Work continues at the Ballantyne Road wetland mitigation site in the Town of Chili. Activities include tree planting, watering and seed planting.

Weeks of 6/25/2018 & 7/2/2018

Construction Update

Construction activities continue at the Ballantyne Road wetland mitigation site in the Town of Chili. Work includes the hauling of clean soils off site, grading of topsoil on site, and tree planting.

Weeks of 6/11/2018 & 6/18/2018

Construction Update

Construction activities will continue at the Ballantyne Road wetland mitigation site in the Town of Chili. Work will include the hauling of clean soils off site, hauling of contaminated soils to a licensed landfill, and grading of topsoil on site.

Weeks of 5/29/2018 & 6/4/2018

Construction Update

Construction activities for this week include:

  • Installation of matting in the Town of Chili between Jetview Drive and Fisher Road;
  • Mobilization of equipment for upcoming excavation related to the underground portion of the new Circuit 940 in the Town of Chili in the vicinity of Jetview Drive;
  • Continuation of work at the wetland mitigation site off of Ballantyne Road in the Town of Chili, including the removal of soils and debris off site and the spreading of clean topsoil on site; and
  • Installation/maintenance of environmental controls as needed to accommodate the Circuit 940 underground work.

Weeks of 5/14/2018 & 5/21/2018

Construction Update

Construction activities will continue this week at the Ballantyne Road wetland mitigation site in the Town of Chili. Work this week will include the hauling of clean soils off site.

5/7/2018

Construction Update

Construction activities will continue this week at the Ballantyne Road wetland mitigation site in the Town of Chili. Work this week will include the removal and relocation of soils and debris on site.

4/30/2018

Construction Update

Construction activities for this week include:

  • Work related to the underground portion of the new Circuit 940 in the Town of Chili, including jack and boring activities in the vicinity of Jetview Drive;
  • Potholing (digging test holes to expose underground facilities) in the Town of Gates in the vicinity of Trabold Road;
  • Continuation of work at the wetland mitigation site off of Ballantyne Road in the Town of Chili, including the removal and relocation of soils and debris on site; and
  • Installation/maintenance of environmental controls as needed to accommodate the Circuit 940 underground work.

4/23/2018

Construction Update

Construction activities for this week include:

  • Work related to the underground portion of the new Circuit 940 in the Town of Chili, including jack and boring activities in the vicinity of Jetview Drive;
  • Potholing (digging test holes to expose underground facilities) in the Town of Chili in the vicinity of Fisher Road;
  • Continuation of work at the wetland mitigation site off of Ballantyne Road in the Town of Chili, including the removal and relocation of soils and digging of test pits; and
  • Installation/maintenance of environmental controls as needed to accommodate the Circuit 940 underground work.

4/16/2018

Construction Update

Construction activities for this week include:

  • Work related to the underground portion of the new Circuit 940 in the Town of Chili, including site preparation and boring activities in the vicinity of Jetview Drive;
  • Matting in the Town of Gates in the vicinity of Trabold Road;
  • Vegetation removal in the Town of Gates in the vicinity of Trabold Road and Pixley Road;
  • Installation/maintenance of environmental controls in the Town of Chili in the vicinity of Fisher Road and Jetview Drive; and
  • Installation of work signs in the Towns of Chili and Gates in the vicinity of Jetview Drive, Buffalo Road and Coldwater Road.

4/9/2018

Construction Update

Construction activities for this week include:

  • The placement of mats in the Town of Gates in the vicinity of Trabold Road;
  • Brush and wood removal in the Town of Gates in the vicinity of Coldwater Road and RG&E's Station 418; and
  • Installation/maintenance of environmental controls in the Town of Gates in the vicinity of Trabold Road, Coldwater Road and Buffalo Road.

4/2/2018

Construction Update

Construction activities for this week include:

  • The placement of mats in the Town of Gates between Buffalo Road and RG&E's Station 418, and in the Town of Chili in the vicinity of Jetview Drive;
  • Brush and wood removal in the Town of Gates in the vicinity of Coldwater Road; and
  • Installation/maintenance of environmental controls as necessary to accommodate underground construction work.

3/26/2018

Construction Update

Construction activities for this week include:

  • The commencement of work activities related to the underground portion of the new Circuit 940 in the Towns of Gates and Chili. Work to be performed this week includes potholing (digging test holes to expose underground facilities) in the vicinity of Pixley Road and Trabold Road, and the commencement of boring activities, including site preparation, in the vicinity of Jetview Drive;
  • The placement of mats in the Town of Gates between Trabold Road and Coldwater Road;
  • Chipping and wood removal in the Town of Gates in the vicinity of Trabold Road; and
  • Installation/maintenance of environmental controls as necessary to accommodate underground construction work.

3/19/2018

Construction Update

Construction activities for this week include:

  • Installation of silt fence in the Town of Gates from Buffalo Road to Station 418 (near the Rochester Technology Park), and from Trabold Road to Coldwater Road;
  • The placement of mats and timbers in the Town of Gates from Trabold Road heading southeast towards the CSX railway, and the installation of gravel access roadways in the same vicinity; and
  • Right-of-way cutting/mowing in the Town of Gates between the CSX railway and Trabold Road. Crews are expected to finish cutting and start hauling debris off site.

3/12/2018

Construction Update

Construction activities for this week include:

  • Installation of silt fence in the Town of Chili from Fisher Road to Westside Drive;
  • The placement of mats and timbers in the Town of Gates from Trabold Road heading southeast towards the CSX railway;
  • Right-of-way cutting/mowing in the Town of Gates from Trabold Road heading southeast towards the CSX railway; and
  • Continuation of work at the Ballantyne Road wetland mitigation site in the Town of Chili. Work this week includes tree and shrub clearing and removal, and topsoil removal.

3/5/2018

Construction Update

Construction activities for this week include:

  • Installation of silt fence in the Town of Chili from Fisher Road to Westside Drive;
  • The placement of mats and timbers in the Town of Gates at Pixley Road;
  • Right-of-way mowing in the Town of Gates from Westside Drive to Pixley Road, and Pixley Road to Route 204; and
  • Continuation of work at the Ballantyne Road wetland mitigation site in the Town of Chili. Work this week includes tree and shrub clearing and removal, and topsoil removal.

2/26/2018

Construction Update

Construction activities for this week include:

  • Commencement of site preparation, including right-of-way mowing and clearing, for the Circuit 940 underground portion in the Town of Chili in the vicinity of Fisher Road and the Wegmans Market Street Campus; and
  • Continuation of work at the Ballantyne Road wetland mitigation site in the Town of Chili. Work this week will include access road development and installation/maintenance of environmental controls.

2/19/2018

Construction Update

Construction activities will continue this week at the Ballantyne Road wetland mitigation site in the Town of Chili. Work this week will include the  installation of environmental controls, access gates and construction entrance, as well as access road development.

2/12/2018

Construction Update

Construction activities are expected to commence this week at the Ballantyne Road wetland mitigation site in the Town of Chili. Work this week will include delineating the limits of disturbance and installation of environmental controls.